Pedestrians passing the construction zone along Ignatian Circle will notice much activity and visible progress, as the framing of the new residence halls begins ahead of the fall 2020 opening.

Concrete foundations have been poured, the storm water retention system has been installed, and reinforcing steel assembly is nearing completion. Interior work will begin in November to connect the mechanical, electrical, and plumbing grids, with framing to be completed over winter break.

These photos taken last week offer a peek behind the construction walls, showing the first-floor framing of both buildings.

Building A, Framing and Sheathing. Oct. 28, 2019.
Alternate View, Building A Framing and Sheathing. Oct. 28, 2019.
Building B Framing. Oct. 28, 2019.
Alternate View, Building B Framing. Oct. 28, 2019.